Letter from Wayne Dyok to James W. Balsiger, October 7, 2014, in response to National Marine Fisheries Service's comments on Initial Study Report on Susitna-Watana Hydroelectric Project.
This document is the response from Alaska Energy Authority (AEA) to the the letter dated September 22, 2014, from the Alaska Regional Office of the National Marine Fisheries Service. That letter respresents the comments from the Juneau Office to AEA's Initial Study Report (ISR) for the Susitna-...
Saved in:
Alternate Title: | Title in subject line: Susitna-Watana Hydroelectric Project, FERC Project No. 14241-000 Letter from James W. Balsiger to Wayne Dyok, September 22, 2014, providing National Marine Fisheries Service's comments on the Initial Study Report for the Susitna-Watana Hydroelectric Project. Initial Study Report. |
---|---|
Main Author: | |
Additional Author(s): | Balsiger, James W., Balsiger, James W. |
Corporate Contributor(s): | Alaska Energy Authority, United States. National Marine Fisheries Service. Alaska Regional Office, |
Report Numbers: | SuWa 306 |
Original Source: | Critique of evaluation of: Initial Study Report. |
Series: | Susitna-Watana Hydroelectric Project document ;
no. 306. |
Subjects: | |
Online Access: | Link to Full Text |
Library Holdings: | Print Versions |
LEADER | 04851ctm a2200685Ia 4500 | ||
---|---|---|---|
001 | 3005194 | ||
003 | SIRSI | ||
005 | 20180109024243.0 | ||
007 | ta | ||
007 | cr cn||||a|||| | ||
008 | 180109e20141007xx b s000 i eng d | ||
040 | |a RLA |c RLA |d RLA | ||
035 | |a (OCoLC)1018419496 | ||
043 | |a n-us-ak | ||
050 | 4 | |a TK1425.S8 |b S92 no. 306 | |
088 | |a SuWa 306 | ||
098 | |a SuWa 00306 | ||
049 | |a RLAA | ||
100 | 1 | |a Dyok, Wayne, |e author. | |
245 | 1 | 0 | |a Letter from Wayne Dyok to James W. Balsiger, October 7, 2014, in response to National Marine Fisheries Service's comments on Initial Study Report on Susitna-Watana Hydroelectric Project. |
246 | 1 | |i Title in subject line: |a Susitna-Watana Hydroelectric Project, FERC Project No. 14241-000 | |
260 | |c 2014 October 7. | ||
300 | |a 3, 28, 17 pages ; |c 28 cm. | ||
336 | |a text |b txt |2 rdacontent | ||
337 | |a unmediated |b n |2 rdamedia | ||
338 | |a volume |b nc |2 rdacarrier | ||
490 | 1 | |a Susitna-Watana Hydroelectric Project document ; |v no. 306 | |
500 | |a Title devised by cataloger. | ||
500 | |a Letterhead: Alaska Energy Authority. | ||
500 | |a "October 7, 2014." | ||
500 | |a ARLIS assigned report number: SuWa 306. | ||
550 | |a Upon receipt by FERC, this document was made available electronically through registration obtained on the FERC Online website, and was emailed to that website's subscribers on October 8, 2014, under the posting number 20141008-5071. | ||
500 | |a This document is posting 20141008-5071 of: [FERC eSubscription to Docket 14241, Susitna-Watana Hydroelectric Project]. -- (Susitna-Watana Hydroelectric Project document ; no. 288). | ||
580 | |a A response to: Letter from James W. Balsiger to Wayne Dyok, September 22, 2014, providing National Marine Fisheries Service's comments on the Initial Study Report for the Susitna-Watana Hydroelectric Project. -- 2014 September 22. -- (Susitna-Watana Hydroelectric Project document ; no. 305). | ||
530 | |a Available also in electronic format on the Internet. | ||
520 | |a This document is the response from Alaska Energy Authority (AEA) to the the letter dated September 22, 2014, from the Alaska Regional Office of the National Marine Fisheries Service. That letter respresents the comments from the Juneau Office to AEA's Initial Study Report (ISR) for the Susitna-Watana Hydroelectric Project (FERC No. 14241). This correspondence consists of a three-page letter dated October 7, 2014, from Wayne Dyok, Susitna-Watana Project Manager at the Alaska Energy Authority, to James W. Balsiger, Alaska Region Administrator, with attachments. The attachments include (1) a comment-response table and (2) the original comment letter with its three enclosures (numbered SuWa 305). The ISR comprises sixty volumes and was first released in June 2014 and completed in 2015. The ISR is required by the Federal Energy Regulatory Commission (FERC) for the licensing of the proposed project, and is numbered SuWa 223. | ||
504 | |a Includes bibliographical references (pages 24-26). | ||
610 | 2 | 0 | |a Susitna-Watana Hydroelectric Project. |
630 | 0 | 0 | |a Initial Study Report. |
650 | 0 | |a Ecological risk assessment |z Alaska |z Susitna River. | |
650 | 0 | |a Hydroelectric power plants |x Environmental aspects |z Alaska |z Susitna River. | |
650 | 0 | |a Dams |x Environmental aspects |z Alaska |z Susitna River. | |
650 | 0 | |a Fishery resources |x Research |z Alaska |z Susitna River Watershed. | |
650 | 0 | |a Aquatic animals |x Research |z Alaska |z Cook Inlet. | |
651 | 0 | |a Susitna River (Alaska) |x Power utilization |x Environmental aspects. | |
610 | 2 | 7 | |a Susitna-Watana Hydroelectric Project. |2 fast |0 (OCoLC)fst01917261 |
650 | 7 | |a Dams. |2 fast |0 (OCoLC)fst01198486 | |
650 | 7 | |a Hydroelectric power plants. |2 fast |0 (OCoLC)fst00964930 | |
650 | 7 | |a Water-power. |2 fast |0 (OCoLC)fst01172317 | |
651 | 7 | |a Alaska |z Susitna River. |2 fast |0 (OCoLC)fst01246005 | |
700 | 1 | |a Balsiger, James W., |e addressee. | |
700 | 1 | 2 | |a Balsiger, James W. |t Letter from James W. Balsiger to Wayne Dyok, September 22, 2014, providing National Marine Fisheries Service's comments on the Initial Study Report for the Susitna-Watana Hydroelectric Project. |
700 | 1 | |i Critique of: |a Balsiger, James W. |t Letter from James W. Balsiger to Wayne Dyok, September 22, 2014, providing National Marine Fisheries Service's comments on the Initial Study Report for the Susitna-Watana Hydroelectric Project. | |
710 | 2 | |a Alaska Energy Authority, |e author. | |
710 | 1 | |a United States. |b National Marine Fisheries Service. |b Alaska Regional Office, |e addressee. | |
730 | 0 | |i Critique of evaluation of: |a Initial Study Report. | |
830 | 0 | |a Susitna-Watana Hydroelectric Project document ; |v no. 306. | |
856 | 4 | 1 | |u https://www.arlis.org/docs/vol1/Susitna2/3/SuWa306.pdf |z ARLIS Document Server |
901 | |a ARLIS |c orig 201801 | ||
596 | |a 9 10 |