Unit prices - backup calculations, Watana Dam/Devil Canyon production rates, Watana.
A collection of hand completed worksheets (called 'Calculations' or 'Estimate work sheet') from Acres American Incorporated regarding estimated costs for the Susitna Hydroelectric Project. These sheets cover all types of facilities including powerhouses, access tunnels and shafts...
Saved in:
Alternate Title: | Book C. Unit prices - backup calculations, Watana Dam/Devil Canyon production rates, Watana. (C). Unit prices - backup calculations, Watana Dam/Devil Canyon production rates, Watana Book C. Watana Dam/Devil Canyon production rates Watana Dam/Devil Canyon production rates Title in the Susitna Hydroelectric Project document index: Watana/Devil Canyon production rates (underground), Book C, Task 9 - Group 12 |
---|---|
Corporate Contributor(s): | Acres American Incorporated. |
Publisher: | Acres American Incorporated, |
Report Numbers: | APA 254 |
Series: | Document (Susitna Hydroelectric Project) ;
no. 254. |
Subjects: | |
Online Access: | Link to Full Text |
Library Holdings: | Print Versions |
LEADER | 02842cam a2200505Ia 4500 | ||
---|---|---|---|
001 | 2038580 | ||
003 | SIRSI | ||
005 | 20140523011043.0 | ||
007 | ta | ||
007 | cr bn||||a|||| | ||
008 | 140520s1982 nyua t 000 0 eng d | ||
040 | |a RLA |c RLA |d RLA | ||
035 | |a (OCoLC)880316639 | ||
043 | |a n-us-ak | ||
050 | 4 | |a TK1425.S8 |b A23 no. 254 | |
088 | |a APA 254 | ||
049 | |a RLAA | ||
130 | 0 | |a Book C. |p Unit prices - backup calculations, Watana Dam/Devil Canyon production rates, Watana. | |
245 | 1 | 0 | |a Unit prices - backup calculations, Watana Dam/Devil Canyon production rates, Watana. |
246 | 3 | |a (C). |p Unit prices - backup calculations, Watana Dam/Devil Canyon production rates, Watana | |
246 | 1 | 4 | |a Book C. |p Watana Dam/Devil Canyon production rates |
246 | 3 | 0 | |a Watana Dam/Devil Canyon production rates |
246 | 1 | |i Title in the Susitna Hydroelectric Project document index: |a Watana/Devil Canyon production rates (underground), Book C, Task 9 - Group 12 | |
260 | |a [Buffalo, N.Y.? : |b Acres American Incorporated, |c 1982] | ||
300 | |a 204 [i.e. 178] p. : |b ill. ; |c 28 cm. | ||
336 | |a text |b txt |2 rdacontent | ||
337 | |a unmediated |b n |2 rdamedia | ||
338 | |a volume |b nc |2 rdacarrier | ||
500 | |a Title from caption on page 2 (table of contents page); page 1 missing? | ||
500 | |a At head of title: (C). | ||
500 | |a Handwritten on cover label: Task 9 - Group 2 [i.e. 12?]. | ||
500 | |a This document belongs to a set of volumes issued by Acres American Incorporated (as indicated in the Susitna Hydroelectric Project document index) that are also called 'Books', such as Book A, Book B, etc. | ||
500 | |a Pages are numbered by hand on the bottom through 204; some pages missing or not included. Total number of pages is 178. | ||
510 | 3 | |a Assigned APA Document no. 254 in the Susitna Hydroelectric Project document index. | |
530 | |a Available also in electronic format on the Internet. | ||
520 | |a A collection of hand completed worksheets (called 'Calculations' or 'Estimate work sheet') from Acres American Incorporated regarding estimated costs for the Susitna Hydroelectric Project. These sheets cover all types of facilities including powerhouses, access tunnels and shafts, fire protection headtanks, cable shafts, surge chambers, penstocks, transformer galleries, and so forth. | ||
610 | 2 | 0 | |a Susitna Hydroelectric Project |x Planning. |
650 | 0 | |a Dams |x Design and construction |x Estimates |z Alaska |z Susitna River. | |
650 | 0 | |a Hydroelectric power plants |x Design and construction |x Estimates |z Alaska |z Susitna River. | |
710 | 2 | |a Acres American Incorporated. | |
830 | 0 | |a Document (Susitna Hydroelectric Project) ; |v no. 254. | |
856 | 4 | 1 | |u https://www.arlis.org/docs/vol1/Susitna/2/APA254.pdf |z ARLIS Document Server |
901 | |a 3755 |c orig | ||
596 | |a 9 10 | ||
098 | |a APA 00254 |