[Letter] 1979 June 13, Washington, D.C. [to] Edwin Kuhn, Washington, D.C.

On December 18, 1978 Edwin Kuhn requested provisional approval for proposed alignment for the Alaska Gas Pipeline (called Northwest Alaskan Gas Pipeline) authorized by the Alaska Natural Gas Transportation Act of 1976. This letter is a response to that request and subsequent letters. A major issue i...

Full description

Saved in:
Bibliographic Details
Main Author: Martin, Guy R.
Corporate Contributor(s):Northwest Alaskan Pipeline Company
Document Type: Memorandum
Publisher:U.S. Department of the Interior. Land and Water Resources
Date:June 13, 1979
Addressee / Recipient:Kuhn, Edwin
Sponsor / Funder:Northwest Alaskan Pipeline Company
Subjects:
Online Access:View Full Text
Library Holdings:Print Versions
Description
Summary:On December 18, 1978 Edwin Kuhn requested provisional approval for proposed alignment for the Alaska Gas Pipeline (called Northwest Alaskan Gas Pipeline) authorized by the Alaska Natural Gas Transportation Act of 1976. This letter is a response to that request and subsequent letters. A major issue is the right-of-way, particularly in regard to shared alignment along the Trans-Alaska Pipeline System.
Physical Description:22 p.
Notes:A four-page memorandum with 5 enclosures. Addressed to Edwin Kuhn, Director, Government and Environmental Affairs, Northwest Alaskan Pipeline Company (also called NAPLINE), from Guy R. Martin, Assistant Secretary, U.S. Department of the Interior, Land and Water Resources.

Date from stamp on first page.

The enclosure contains these attachments: Enclosure. [Letter, 1979, Washington, D.C. [to] J.F. McPhail, Houston, Texas] [Addressed to J.F. McPhail, Manager, ANGTS, Task Force, Ex[x]on Pipeline Company, from [Guy R. Martin], Assistant Secretary, U.S. Department of the Interior, Land and Water Resources] (1 p.) -- Enclosure A. Report and recommendations on Northwests's request for provisional approval of the Alaska Gas Pipeline alignment : [letter, 1979 June 7, Anchorage, Alaska to Assistant Secretary, Land and Water Resources, Washington, D.C.] (4 p.) -- Enclosure B. Summary of working group assumptions and conclusions, May 24, 1979. (2 p.) -- Working group questions/concerns, May 24, 1979. (2 p.) -- Enclosure D. Mile-by-mile route statement. (9 p.).