United States of America before the Federal Energy Regulatory Commission : docket no. CP80- : application of Alaskan Northwest Natural Gas Transportation Company for a final certificate of public convenience and necessity pursuant to Section 7 (c) of the Natural Gas Act, as amended, and Section 9 of the Alaska Natural Gas Transportation Act of 1976 to construct and operate the Alaska segment of the Alaska Natural Gas Transportation System

Saved in:
Bibliographic Details
Alternate Title:United States of America before the Federal Energy Regulatory Commission : application of Alaskan Northwest Natural Gas Transportation Company : docket no. CP80- : for a final certificate of public convenience and necessity authorizing the construction and operation of the Alaska segment of the Alaska Natural Gas Transportation System
Corporate Author: Alaskan Northwest Natural Gas Transportation Company (ANNGTC)
Corporate Contributor(s):Federal Energy Regulatory Commission (FERC)
Document Type: Legal
Publisher:Alaskan Northwest Natural Gas Transportation Company (ANNGTC)
Report Numbers:Docket no. CP80-
Date:July 1, 1980
Bills/Acts; Orders; Treaties:Natural Gas Act of 1938 (NGA)

Alaska Natural Gas Transportation Act of 1976 (ANGTA)
Sponsor / Funder:Federal Energy Regulatory Commission (FERC)
Series:Alaska Segment : Alaska Natural Gas Transportation System
Subjects:
Online Access:View Full Text
View Full Text
Library Holdings:Print Versions
Contents:
  • v. 1. Application, federal register notice, overall table of contents, Exhibits A through J inclusive and Exhibits L through P inclusive
  • v. 2. Exhibit K, Certification of cost and schedule estimate
  • v. 3. Exhibit Z-1.1, Environmental engineering manual
  • v. 4. Exhibit Z-2, Description of gas processing facilities. Exhibit Z-3, [Description of Canadian facilities]. Exhibit Z-4, [Description of Lower 48 facilities]. Exhibit Z-5, [Reliability and compatibility related facilities] [Exhibits Z-3 to Z5 not released]
  • v. 5. Exhibit Z-7, Center point justification
  • v. 6. Design manual, Exhibit Z-9.0, Design summary
  • v. 6., errata 1. Design manual, Exhibit Z-9.0, Design summary
  • v. 7. Design manual, Exhibit Z-9.1, Pipeline and civil design
  • v. 8. Design manual, Exhibit Z-9.2, Compressor and metering station design. Exhibit Z-9.3, Communications system design. Exhibit Z-9.4, Operations and maintenance facility design. Exhibit Z-9.5. Temporary facilities design
  • v. 10. Construction and logistics plan WP-4, work papers in support of Exhibit K
  • Supplement to application for right-of-way grant (5 v.).