Proposal to eliminate the Chulitna Corridor from further study /
The Chulitna Corridor has been one of three access and transmission corridors that the Alaska Energy Authority (AEA) has been evaluating for the Susitna-Watana Hydroelectric Project. This corridor runs north of the Susitna River and extends to the Chulitna rail siding. AEA is reconsidering its corri...
Saved in:
Corporate Author: | |
---|---|
Corporate Contributor(s): | Susitna-Watana Hydroelectric Project. |
Publisher: | Alaska Energy Authority, |
Report Numbers: | SuWa 229 |
Series: | Susitna-Watana Hydroelectric Project document ;
no. 229. |
Subjects: | |
Online Access: | Link to Full Text Link to Full Text |
Library Holdings: | Print Versions |
LEADER | 03023cam a2200493Ia 4500 | ||
---|---|---|---|
001 | 2384045 | ||
003 | SIRSI | ||
005 | 20150407013658.0 | ||
007 | ta | ||
007 | cr cn||||a|||| | ||
008 | 150331s2014 aku s000 0 eng d | ||
040 | |a RLA |c RLA |d RLA | ||
035 | |a (OCoLC)905915348 | ||
043 | |a n-us-ak | ||
050 | 4 | |a TK1425.S8 |b S92 no. 229 | |
088 | |a SuWa 229 | ||
049 | |a RLAA | ||
110 | 2 | |a Alaska Energy Authority. | |
245 | 1 | 0 | |a Proposal to eliminate the Chulitna Corridor from further study / |c prepared by Alaska Energy Authority. |
260 | |a [Anchorage : |b Alaska Energy Authority, |c 2014] | ||
300 | |a 2 p. ; |c 28 cm. | ||
336 | |a text |b txt |2 rdacontent | ||
337 | |a unmediated |b n |2 rdamedia | ||
338 | |a volume |b nc |2 rdacarrier | ||
490 | 1 | |a Susitna-Watana Hydroelectric Project document ; |v no. 229 | |
500 | |a "Susitna-Watana Hydroelectric Project (FERC No. 14241)." | ||
500 | |a "September 2014." | ||
500 | |a ARLIS assigned report number: SuWa 229. | ||
510 | 3 | |a Listed in September 2014 on the Susitna-Watana Hydroelectric Project's Document webpage under the category: September 17, 2014 technical memorandum filings. | |
513 | |a September 17, 2014 technical memorandum filings. | ||
500 | |a This document was filed to FERC as Attachment A to: Susitna-Watana Hydroelectric Project, FERC Project no. 14241-000; Initial filing of September 2014 technical memoranda. (SuWa 228). | ||
530 | |a Available also in electronic format on the Internet. | ||
650 | 4 | |a Access roads |z Alaska |z Susitna River Valley. | |
520 | |a The Chulitna Corridor has been one of three access and transmission corridors that the Alaska Energy Authority (AEA) has been evaluating for the Susitna-Watana Hydroelectric Project. This corridor runs north of the Susitna River and extends to the Chulitna rail siding. AEA is reconsidering its corridor options, however, and would like to include a Denali East Option, but eliminate the Chulitna Corridor from further study. | ||
610 | 2 | 0 | |a Susitna-Watana Hydroelectric Project. |
650 | 4 | |a Dams |x Access roads |z Alaska |z Susitna River Valley. | |
650 | 0 | |a Transportation |z Alaska |z Susitna River Valley |x Planning. | |
710 | 2 | |a Susitna-Watana Hydroelectric Project. | |
787 | 0 | 8 | |i Originally submitted as Attachment A to: |a Dyok, Wayne. |t Susitna-Watana Hydroelectric Project, FERC Project no. 14241-000; Initial filing of September 2014 technical memoranda. |d [Anchorage : Alaska Energy Authority, 2014] |k Susitna-Watana Hydroelectric Project document ; no. 228 |r SuWa 228 |w (OCoLC)905914340 |
830 | 0 | |a Susitna-Watana Hydroelectric Project document ; |v no. 229. | |
856 | 4 | 1 | |u https://www.arlis.org/docs/vol1/Susitna2/2/SuWa229.pdf |3 Direct link to this document. |z ARLIS Document Server |
856 | 4 | 2 | |u https://www.arlis.org/docs/vol1/Susitna2/2/SuWa228.html |3 List of all technical memorandums that were submitted as attachments to the cover letter filed to FERC on September 17, 2014 (SuWa 228). |z ARLIS Document Server |
596 | |a 9 10 | ||
098 | |a SuWa 00229 |