21
by Persily, Larry
Published July 30, 2018
Contents: '; ...The Alaska Department of Natural Resources asked federal regulators if its permitting office can...
Direct link to this update
Website listing all Project updates
22
by Persily, Larry
Published August 31, 2018
Contents: '; ... schedule for the Alaska LNG project's environmental impact statement and commission decision. This effects...
Direct link to this update
Website listing all Project updates
23
by Persily, Larry
Published January 6, 2020
Contents: '; ...The Alaska Gasline Development Corporation completed its answers to questions from federal...
Direct link to this update
Website listing all Project updates
24
by Persily, Larry
Published October 26, 2015
Contents: '; ...The Alaska LNG Project would require several miles of the Kenai Spur Highway to be relocated away...
Direct link to this update
Website listing all Project updates
25
by Persily, Larry
Published October 8, 2015
Contents: '; ... to hear from the public on the Alaska LNG Project. The meetings are taking place between October 27...
Direct link to this update
Website listing all Project updates
26
by Persily, Larry
Published March 13, 2018
Contents: '; ...The Federal Energy Regulatory Commission published its timeline for Alaska LNG Project...
Direct link to this update
Website listing all Project updates
27
by Persily, Larry
Published July 10, 2018
Contents: '; ... wetland mitigation plan for the proposed Alaska LNG Project. Meanwhile, the AGDC is still working on its...
Direct link to this update
Website listing all Project updates
28
by Persily, Larry
Published May 29, 2020
Contents: '; ...Federal authorization for the Alaska LNG Project sets a 10-year deadline to start operating the gas...
Direct link to this update
Website listing all Project updates
29
by Brough, Jennifer
Published September 5, 2014
Contents: '; ... of Alaska LNG Project LLC for long-term authorization to export liquefied natural gas" filed on July 18...

Report Number(s): Docket No. 14-96-LNG

Link to full text
30
by Persily, Larry
Published July 7, 2017
Contents: '; ...The Federal Energy Regulatory Commission delivered a 55-page list of questions to Alaska Gasline...
Direct link to this update
Website listing all Project updates
31
Published February 2, 2015
Subjects: '; ...Alaska LNG Project...

Report Number(s): Docket no. PF14-21-000 USAKE-PT-SRREG-00-0001 USAI-EX-SRREG-00-0001

Link to main report of No. 1
Webpage for the full Draft resource report
33
by Persily, Larry
Published June 29, 2020
Contents: '; ...An updated cost estimate for the proposed Alaska LNG project has trimmed $5 billion from...
Direct link to this update
Website listing all Project updates
34
by Persily, Larry
Published July 11, 2022
Contents: '; ... for the Alaska LNG Project on June 24 for public comment. FERC published its final impact statement in 2020...
Direct link to this update
Website listing all Project updates
35
Published October 1, 2014
Subjects: '; ...Alaska LNG Project...

Report Number(s): Docket no. PF14-21-000 USAKE-PT-SRREG-00-0001 USAKE-PT-SRREG-00-0010

Link to report No. 1
Webpage listing all volumes
36
Published October 8, 2014
Contents: '; ...This is a summary of "Alaska LNG Project, Docket no. PF14-21-000, preliminary resource report...
Link to this summary
Webpage listing all volumes of "Preliminary resource report 1"
37
by Martin, James
Published December 11, 2014
Contents: '; ...This document is a set of comments on "Alaska LNG Project, Docket no. PF14-21-000, preliminary...

Report Number(s): Docket no. PF14-21-000

Link to full text
39
Contents: '; .... (With: Attachment 1. Description of acres acquired, liquefaction facility site, Nikiski, Alaska. Attachment 2...

Report Number(s): Docket No. 14-96-LNG

Link to full text
40
by Butt, Steve, Fauske, Dan, Meznarich, Darren
Published September 5, 2014
Contents: '; ... (as required by FERC) for the Alaska LNG Project. Those applicants are BP Alaska LNG LLC, ConocoPhillips Alaska...

Report Number(s): Docket No. PF14-...-000 USAI-PE-SGEIS-00-0003

Link to full text