State response timeline adds 4 months to EIS schedule
Citing the state's timeline for answering federal regulators’ questions and fulfilling data requests, the Federal Energy Regulatory Commission (FERC) has announced it will issue the draft environmental impact statement for the Alaska LNG Project in June, 2019 (with a similar delay for the final...
Saved in:
Alternate Title: | State response timeline adds four months to environmental impact statement schedule |
---|---|
Main Author: | |
Document Type: | Press release |
Publisher: | Alaska Resources Library and Information Services (ARLIS) |
Date: | February 28, 2019 |
Series: | Alaska LNG Project updates
|
Subjects: | |
Online Access: | View Full Text View Full Text |
Library Holdings: | Print Versions |
Summary: | Citing the state's timeline for answering federal regulators’ questions and fulfilling data requests, the Federal Energy Regulatory Commission (FERC) has announced it will issue the draft environmental impact statement for the Alaska LNG Project in June, 2019 (with a similar delay for the final EIS), which represents a four-month extension. the Alaska Gasline Development Corp. (AGDC) owes FERC information on safety, construction, and earthquake fault crossings. AGDC's current budget situation is also discussed. |
---|---|
Physical Description: | 2 pages |
Notes: | This update is provided to keep the public informed about the Alaska LNG Project. |