FERC moves up Alaska project schedule 1 month

On August 31, 2018, the Federal Energy Regulatory Commission (FERC) moved up by one month its schedule for the Alaska LNG project's environmental impact statement and commission decision. This effects the draft impact statement (now February 2019), the final impact statement (now November 2019)...

Full description

Saved in:
Bibliographic Details
Main Author: Persily, Larry
Document Type: Press release
Publisher:Alaska Resources Library and Information Services (ARLIS)
Date:August 31, 2018
Series:Alaska LNG Project updates
Subjects:
Online Access:View Full Text
View Full Text
Library Holdings:Print Versions
LEADER 01559cam a22003133 4500
001 5052203
003 SIRSI
008 180904s2018 o 000 0 eng u
100 1 |a Persily, Larry 
245 1 0 |a FERC moves up Alaska project schedule 1 month 
260 |a Alaska Resources Library and Information Services (ARLIS) 
264 |a 20180831 
300 |a 2 p. 
380 |a Press release 
490 |a Alaska LNG Project updates 
518 |a August 31, 2018 
546 |a English 
500 |a This update is provided to keep the public informed about the Alaska LNG Project. 
520 |a On August 31, 2018, the Federal Energy Regulatory Commission (FERC) moved up by one month its schedule for the Alaska LNG project's environmental impact statement and commission decision. This effects the draft impact statement (now February 2019), the final impact statement (now November 2019), and application decision (now February 2020). Meanwhile, the project team filed more details to FERC on August 15 on project design and operations. 
610 2 |a Alaska LNG Project 
610 2 |a Federal Energy Regulatory Commission (FERC) 
653 |a Environmental analysis 
653 |a Schedule 
690 |a PF-AKGOV 
690 |a PF-ENVI 
856 4 1 |u https://www.arlis.org/docs/vol1/AlaskaGas/News/News_Persily-2018_FERC_MovesUpAK_ProjectSchedule.pdf  |3 Direct link to this update 
856 4 2 |u https://www.arlis.org/docs/vol1/AlaskaGas/News/News_KPB_AK_LNG_ProjectUpdate.html  |3 Website listing all Project updates 
901 |a ARLIS  |c orig 201809 
596 |a 10