21
Published [1982]

Report Number(s): APA 1370

Link to full text
22
Published [1981]
Subjects: '; ...Dams Alaska Susitna River Design and construction Costs....

Report Number(s): APA 1356

Link to full text
24
Published [1981]
Contents: '; ... in the Railbelt region -- Cooling water systems in steam cycle plants -- Fuel availability and prices -- Aesthetic...

Report Number(s): APA 567 (draft)

Link to full text
25
Published [1984]
...Susitna Hydroelectric Project. Feasibility level project cost estimate, Watana Dam and reservoir...

Report Number(s): APA 1457

Link to full text
26
Published [1982]
Contents: '; ...Identification of access alternatives -- Cost of access alternatives -- Risk to project schedule...

Report Number(s): APA 5 APA 287 APA 1340 APA 1582 SUS 79

Link to full text
27
Published 1982]
Subjects: '; ...Overhead costs....

Report Number(s): APA 258

Link to full text
28
Published 1981]
...Added title page title (page 1): Unit prices - backup calculations, Watana Dam, quantities/borrow...

Report Number(s): APA 257

Link to full text
29
Published 1984]
Subjects: '; ...Dams Alaska Susitna River Design and construction Costs....

Report Number(s): APA 1918

Link to full text
30
Published [1981]
Subjects: '; ...Hydroelectric power plants Alaska Susitna River Costs....

Report Number(s): APA 93

Link to full text
Link to full text
31
Published [1985]
...Susitna Hydroelectric Project. Definition and costs of thermal power alternatives to Susitna...

Report Number(s): APA 2920 SUS 585

Link to full text
32
Published [1983]
Subjects: '; ...Hydroelectric power plants Alaska Susitna River Design and construction Costs....

Report Number(s): APA 3264

Link to full text
33
Published 1982]
...Caption title on page 1 (table of contents page): Unit prices - backup calculations, Watana Dam...

Report Number(s): APA 256

Link to full text
34
Published [1981]
Contents: '; ...Introduction -- Summary -- Scope -- Previous studies -- Design parameters -- Construction cost...

Report Number(s): APA 1276 APA 2787 SUS 63

Link to full text
35
Published [1982]
Subjects: '; ...Dams Alaska Susitna River Design and construction Costs....

Report Number(s): APA 1359

Link to full text
36
Published [1982]
Subjects: '; ...Dams Alaska Susitna River Design and construction Costs....

Report Number(s): APA 1358

Link to full text
37
Published [1984]
...Feasibility level, summary of cost estimate...

Report Number(s): APA 2493 APA 2494

Direct link to the first section.
List of all sections.
38
Published [1981]
Subjects: '; ...Dams Alaska Susitna River Design and construction Costs....

Report Number(s): APA 1357

Link to full text
39
Published [1982]
...Susitna Hydroelectric Project. Feasibility report. Volume 6, Appendix C, Cost estimates, Final...

Report Number(s): APA 1423

Direct link to Volume 6, Appendix C.
Link to the feasability report (final draft) and list of all documents related to it.
40
by Debelius, C. A.
Published [1980]
Subjects: '; ...Airports Alaska Susitna River Valley Costs....

Report Number(s): APA 1218

Link to full text