“...Dams Alaska Susitna River Design and construction Costs....”Report Number(s): APA 1356
Link to full text
2
3
Published [1984]
“...Susitna Hydroelectric Project. Feasibility level project cost estimate, Watana Dam and reservoir...”Report Number(s): APA 1457
Link to full text
4
Published [1982]
Contents: ';
“...Identification of access alternatives -- Cost of access alternatives -- Risk to project schedule...”Report Number(s): APA 5 APA 287 APA 1340 APA 1582 SUS 79
Link to full text
5
Published [1982]
Subjects: ';
“...Dams Alaska Susitna River Design and construction Costs....”Report Number(s): APA 1359
Link to full text
6
Published [1982]
Subjects: ';
“...Dams Alaska Susitna River Design and construction Costs....”Report Number(s): APA 1358
Link to full text
7
Published [1981]
Subjects: ';
“...Dams Alaska Susitna River Design and construction Costs....”Report Number(s): APA 1357
Link to full text
8
Published [1982]
“...Susitna Hydroelectric Project. Feasibility report. Volume 6, Appendix C, Cost estimates, Final...”Report Number(s): APA 1423
Direct link to Volume 6, Appendix C.Link to the feasability report (final draft) and list of all documents related to it.
9
Published [1982]
“... and economic aspects...”Report Number(s): APA 1291 APA 1292
Direct link to Sections 1-8.Link to all sections.
Link to the feasability report (final draft) and list of all documents related to it.
10
Published [1984]
“...Susitna Hydroelectric Project. Explanation of August 1984 revised cost estimate...”Report Number(s): APA 1919 APA 1920