Unit prices - backup calculations, Watana Dam, breakdown of equipment costs.
A collection of hand completed worksheets (called 'Calculations') from Acres American Incorporated regarding estimated construction equipment costs for the Susitna Hydroelectric Project. These sheets cover cofferdams, rip-rap, excavation of overburden, reusable rock, and rock waste.
Saved in:
Alternate Title: | Book H. Unit prices - backup calculations, Watana Dam, breakdown of equipment costs. (H). Unit prices - backup calculations, Watana Dam, breakdown of equipment costs |
---|---|
Corporate Contributor(s): | Acres American Incorporated. HARZA-EBASCO Susitna Joint Venture. |
Publisher: | Acres American Incorporated, |
Report Numbers: | APA 106 |
Series: | Document (Susitna Hydroelectric Project) ;
no. 106. |
Subjects: | |
Online Access: | Link to Full Text |
Library Holdings: | Print Versions |
Summary: | A collection of hand completed worksheets (called 'Calculations') from Acres American Incorporated regarding estimated construction equipment costs for the Susitna Hydroelectric Project. These sheets cover cofferdams, rip-rap, excavation of overburden, reusable rock, and rock waste. |
---|---|
Physical Description: | 16 p. ; 28 cm. |
Notes: | At head of title: (H). Series statement from label on title page. This document belongs to a set of volumes issued by Acres American Incorporated (as indicated in the Susitna Hydroelectric Project document index) that are also called 'Books', such as Book A, Book B, etc. Cataloging based on copy with no page numbered 1 (perhaps the title page) or 2. |