Task 6, design development. Subtask 6.02, Closeout report, investigate tunnel alternative.
"The objective of the Subtask 6.02 study is to undertake a preliminary assessment of the feasibility of using a major tunnel to develop hydroelectric power on the Susitna River between the proposed Watana and Devil Canyon dam sites."--P. 1-1.
Saved in:
Alternate Title: | Alaska Power Authority, Susitna Hydroelectric Project. Task 6, Design development. Subtask 6.02, Closeout report, investigate tunnel alternative Subtask 6.02, Closeout report, investigate tunnel alternative Investigate tunnel alternative |
---|---|
Corporate Contributor(s): | Alaska Power Authority. Acres American Incorporated. |
Publisher: | Acres American Incorporated, |
Report Numbers: | APA 1279 |
Edition: | Final draft. |
Series: | Document (Susitna Hydroelectric Project) ;
no. 1279. |
Subjects: | |
Online Access: | Link to Full Text |
Library Holdings: | Print Versions |
LEADER | 02467cam a2200481Ia 4500 | ||
---|---|---|---|
001 | 2018513 | ||
003 | SIRSI | ||
005 | 20140214104822.0 | ||
007 | cr bn||||a|||| | ||
008 | 140214s1981 nyuab bt 000 0 eng d | ||
035 | |a (OCoLC)870539742 | ||
040 | |a RLA |c RLA |d RLA | ||
049 | |a RLAA | ||
050 | 4 | |a TK1425.S8 |b A23 no. 1279 | |
088 | |a APA 1279 | ||
245 | 0 | 0 | |a Task 6, design development. |n Subtask 6.02, |p Closeout report, investigate tunnel alternative. |
246 | 3 | |a Alaska Power Authority, Susitna Hydroelectric Project. |n Task 6, |p Design development. |n Subtask 6.02, |p Closeout report, investigate tunnel alternative | |
246 | 3 | 0 | |a Subtask 6.02, |p Closeout report, investigate tunnel alternative |
246 | 3 | 0 | |a Investigate tunnel alternative |
250 | |a Final draft. | ||
260 | |a Buffalo, N.Y. : |b Acres American Incorporated, |c [1981] | ||
300 | |a 74 p. in various pagings : |b ill., maps ; |c 28 cm. | ||
336 | |a text |2 rdacontent | ||
337 | |a computer |2 rdamedia | ||
338 | |a online resource |2 rdacarrier | ||
500 | |a At head of title: Alaska Power Authority, Susitna Hydroelectric Project. | ||
500 | |a "March 1981." | ||
510 | 3 | |a Assigned APA Document no. 1279 in the Susitna Hydroelectric Project document index. | |
530 | |a Available also in electronic format on the Internet. | ||
520 | |a "The objective of the Subtask 6.02 study is to undertake a preliminary assessment of the feasibility of using a major tunnel to develop hydroelectric power on the Susitna River between the proposed Watana and Devil Canyon dam sites."--P. 1-1. | ||
505 | 0 | |a Introduction -- Summary -- Scope of work -- Conceptual tunnel schemes -- Tunnel design and construction considerations -- Screening of conceptual tunnel schemes -- Preferred tunnel scheme -- Comparison with Devil Canyon dam scheme -- Conclusions and recommendations. | |
504 | |a Includes bibliographical references. | ||
610 | 2 | 0 | |a Susitna Hydroelectric Project. |
650 | 0 | |a Water tunnels |z Alaska |z Susitna River Valley |x Design and construction. | |
650 | 0 | |a Underground electric power plants |z Alaska |z Susitna River Valley |x Design and construction. | |
710 | 2 | |a Alaska Power Authority. | |
710 | 2 | |a Acres American Incorporated. | |
830 | 0 | |a Document (Susitna Hydroelectric Project) ; |v no. 1279. | |
043 | |a n-us-ak | ||
856 | 4 | 1 | |u https://www.arlis.org/docs/vol1/Susitna/12/APA1279.pdf |z ARLIS Document Server |
901 | |a 3755 |c orig | ||
596 | |a 9 10 | ||
098 | |a APA 01279 |