Revised Study plan, Susitna-Watana Hydroelectric Project, FERC No. 14241

Alaska Energy Authority
Susitna-Watana Hydroelectric Project

[Anchorage : Alaska Energy Authority, 2012]

December 2012.


 

LINKS VIA ARLIS DOCUMENT SERVER:

SuWa NumberSection
76 Cover letter

To Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, from Wayne Dyok, Project Manager, Alaska Energy Authority

Sections 1-5: Intro through water quality

Introduction to RSP -- Proposed 2013 and 2014 ILP studies -- Studies not proposed -- Geology and soils -- Water quality

Section 6: Geomorphology
Sections 7-8: Hydrology through instream flow studies

Hydrology-related resources -- Instream flow study: fish, aquatics, and riparian

Section 9: Fish and aquatic resources
Section 10: Wildlife resources
Sections 11-12: Botanical through recreation
Sections 13-16: Cultural, subsistence, socioeconomic, project safety

Cultural and paleontological resources -- Subsistence resources -- Socioeconomics and transportation resources -- Project safety

77 Appendix 1, Comment response table of FERC-filed comments
78 Appendix 2, FERC-filed letters coded with comment identifiers
79 Appendix 3, Comment response table of informal consultation, July-November 2012
80 Appendix 4, Consultation documentation for informal consultation, July-November 2012
81 Appendix 5, Mapping references

Document related to the Revised study plan:
Submission of USFWS and NMFS study requests crosswalk tables.   (SuWa 75).