July 11, 2022 |
Draft supplemental EIS says Alaska LNG would not add to greenhouse gases |
July 6, 2021 |
Energy Department orders lifecycle review of Alaska LNG emissions |
July 27, 2020 |
FERC denies requests for rehearing of Alaska LNG approval |
June 29, 2020 |
New estimate reduces Alaska LNG project cost, but economics still challenging |
June 22, 2020 |
Mat-Su Borough asks FERC to reconsider Port MacKenzie for LNG plant |
May 29, 2020 |
FERC approval gives Alaska LNG 10 years to start operations |
May 21, 2020 |
FERC approves Alaska LNG project |
May 13, 2020 |
AGDC looks for new sponsor to take over LNG project — or it will sell off the assets |
March 9, 2020 |
FERC issues final EIS for Alaska project |
January 6, 2020 |
State finishes answering questions for Alaska LNG final EIS |
October 21, 2019 |
Mat-Su and Kenai boroughs continue arguing over project site review |
October 9, 2019 |
Comments on draft EIS cite environmental issues, LNG terminal location |
September 30, 2019 |
Mat-Su Borough wants another review of Port MacKenzie site |
September 23, 2019 |
Valdez and environmental law group both ask more time to response to Draft EIS |
July 29, 2019 |
FERC sets eight public meetings in September on draft EIS |
July 16, 2019 |
AGDC cuts staff; Valdez complains about draft EIS; competing projects move forward |
July 1, 2019 |
Draft EIS says LNG project could have significant environmental impacts |
June 4, 2019 |
State answers FERC questions about Cook Inlet pipeline crossing |
May 7, 2019 |
State nearing the end of project information owed to FERC |
March 11, 2019 |
AGDC stays on schedule with latest batch of answers to FERC |
February 28, 2019 |
State response timeline adds 4 months to EIS schedule |
February 18, 2019 |
AGDC criticizes Mat-Su Borough for 'factual and legal errors' |
February 11, 2019 |
State still owes a lot of information to FERC, but no indication of change in EIS schedule |
January 28, 2019 |
Mat-Su Borough says AGDC analysis of Port MacKenzie is inadequate |
January 16, 2019 |
AGDC says it needs until June to answer more of FERC's engineering questions |
December 18, 2018 |
State will submit rest of Cook Inlet crossing information by September |
December 18, 2018 |
FERC denies state request for cooperating agency status in EIS |
November 27, 2018 |
State tells FERC of problems with Mat-Su Borough's proposed site at Port MacKenzie |
November 8, 2018 |
AGDC project schedule calls for work to begin first-quarter 2020 |
October 24, 2018 |
AGDC meets with FERC to review what's needed to stay on schedule |
October 18, 2018 |
Mat-Su, Kenai boroughs continue sparring over LNG plant site |
October 5, 2018 |
AGDC defends LNG site selection, calls Mat-Su claims 'baseless' |
October 3, 2018 |
FERC sends 63 pages of questions for LNG project |
September 18, 2018 |
Mat-Su says FERC should stop Alaska LNG review until 'fair and accurate' analysis of port site |
September 12, 2018 |
FERC approves Kenai Borough as intervenor in Alaska LNG |
August 31, 2018 |
FERC moves up Alaska project schedule 1 month |
August 15, 2018 |
Kenai Borough files with FERC to defend Nikiski as LNG project site |
July 30, 2018 |
State wants to participate in federal EIS for Alaska LNG project |
July 23, 2018 |
AGDC says Port MacKenzie "not feasible" for LNG terminal |
July 10, 2018 |
Army Corps adds wetlands questions to Alaska LNG work list |
June 12, 2018 |
FERC requests additional sediment modeling work |
April 13, 2018 |
State will answer most of FERC's questions by June; last items Aug. 1 |
March 28, 2018 |
FERC wants project to submit more specific mitigation measures |
March 13, 2018 |
State looks for clarification before answering some of FERC's questions |
March 13, 2018 |
FERC sets Alaska LNG schedule, with December 2019 for final EIS |
February 15, 2018 |
FERC advises state it is falling short in providing information for EIS |
January 15, 2018 |
Mat-Su Borough challenges Nikiski selection for LNG plant site |
December 21, 2017 |
State continues answering questions for environmental review |
November 17, 2017 |
State asks FERC for 'immediate action' on environmental review |
October 13, 2017 |
State responds to last of FERC's initial data requests; waits for EIS schedule |
August 31, 2017 |
State still expects FERC to issue EIS schedule this fall |
August 10, 2017 |
State advises FERC some answers will take until January 2018 |
July 7, 2017 |
FERC sends 55-page data request to state in review of Alaska LNG |
June 8, 2017 |
LNG market could get worse before it gets better |
May 30, 2017 |
Alaska LNG filing attracts opponents, supporters |
April 27, 2017 |
State corporation awaits FERC review of LNG project application |
March 7, 2017 |
State signs on to cover costs of FERC-approved contractor for EIS |
February 15, 2017 |
Supporters push for more consideration of Valdez LNG site |
December 28, 2016 |
FERC sends final questions on draft reports to Alaska LNG : Federal review in holding pattern, awaiting project applicant responses |
November 30, 2016 |
Denali Park pipeline routing waits on congressional action |
November 22, 2016 |
FERC sends more comments, questions to Alaska LNG |
November 15, 2016 |
FERC sends 266 pages of comments, questions to Alaska LNG |
September 1, 2016 |
Regulators continue review of LNG project reports |
June 28, 2016 |
Alaska LNG provides more details on project construction |
April 26, 2016 |
Alaska LNG outlines issues for next round of resource reports |
March 16, 2016 |
'Homeless LNG' likely to keep market oversupplied this decade |
March 10, 2016 |
Next round of LNG project reports to FERC expected to start late spring |
February 19, 2016 |
Weak market could delay Alaska LNG project |
December 28, 2015 |
Alaska LNG working to answer agencies' questions |
December 14, 2015 |
Public submits wide-ranging comments to FERC |
October 26, 2015 |
Alaska LNG project shares information on possible highway relocation |
October 22, 2015 |
FERC schedules 12 hearings statewide on LNG project |
October 13, 2015 |
FERC has full workload with LNG export projects |
October 8, 2015 |
FERC asks public what should be covered in Alaska LNG review |
October 7, 2015 |
Hard times, hard decisions for LNG projects |
September 16, 2015 |
LNG plant construction a huge undertaking |
August 26, 2015 |
Cook Inlet pipeline crossing is about making the best choices |
July 7, 2015 |
Pipeline building a choreography of coordinated steps |
June 9, 2015 |
Tokyo Gas sees Alaska in potential LNG supply mix |
May 29, 2015 |
Energy Department approves Alaska LNG exports |
May 26, 2015 |
Alaska LNG reviews pipeline route with government agencies |